BNC Series
○ Assembly Instruction(3)
Parts Configulration
(for 2.5D-2V)
(for 2.5D-2V)
(for 1.5D-2V / RG-179B/U)
(for 1.5D-2V / RG-179B/U)
Ferule
Ferule
Unit:mm
Contact Assembly
Contact Assembly
Plug Body
Plug Body
①
20mm
① Cut the cable as fig.1.
20mm
● Please be careful to not damage the outer conductor.
②
Ferule
Ferule
2.5D-2V
Inserting Tool
Inserting Tool
② Insert the ferule.
● In case of 2.5D-2V cable, insert the ferule into the cable
and push the ferule between sheath and outer conductor
2.5D-2V
until the head of ferule is reached to the sheath by
inserting tool(E3001-160) and pick the outer conductor.
1.5D-2V,RG-179B/U
1.5D-2V,RG-179B/U
Ferule
Ferule
● In case of 1.5D-2V or RG-179B/U cable , insert the
ferule until the ferule reached at the sheath and pick the
outer conductor.
③ Folding down the outer conductor to the ferule and
A
17mm
cut the couter conductor along the ferule as fig.3.
③
A
1170mmmm
10mm
Cut the insulator and center conductor and pre-solder
the center conductor.
Applicable Cable
2.5D-2V
1.5-2V, RG-179B/U
A
4mm
5mm
④
Soldering
Soldering
1mm
1mm crimping
crimping
④ Insert the contact assembly into the above cable
assembly. Solder up the contact with center conductor
and crimp the root of the contact assembly.
⑤ Insert the body into the above cable assembly and
⑤
screw up the body by the wrench tightly.
Recommended Tightening Torque : 196 N・cm(20kgf・cm)
◎ Please acknowledge that the specification etc. of this catalog might change by the improvement etc. without notice.
Moreover, the characteristic and the specification of the published product are the reference values.
Please confirm the content with the latest delivery specifications when you use the product.
http://www.ddknet.co.jp
11